Section 1 Quiz: Program Management
Get ready to take a short quiz! You can take the quiz as many times as necessary to achieve a passing score. This Quiz should be completed in 30 minutes. 70% of the correct answers are required to pass.
Quiz Summary
0 of 9 Questions completed
Questions:
Information
You will not be able to take the quiz or exam until you select the agreement box and fill in your name.
You have already completed the quiz before. Hence you can not start it again.
Quiz is loading…
You must sign in or sign up to start the quiz.
You must first complete the following:
Results
Results
0 of 9 Questions answered correctly
Your time:
Time has elapsed
You have reached 0 of 0 point(s), (0)
Earned Point(s): 0 of 0, (0)
0 Essay(s) Pending (Possible Point(s): 0)
Categories
- Not categorized 0%
-
PASS: No. Try Again
-
PASS: YES. Congratulations!
- 1
- 2
- 3
- 4
- 5
- 6
- 7
- 8
- 9
- Current
- Review
- Answered
- Correct
- Incorrect
-
Question 1 of 9
1. Question
Before beginning each Definable Feature of Work, the contractor performing that work activity shall prepare __________________.
CorrectIncorrect -
Question 2 of 9
2. Question
The contractor shall identify each major phase that will be performed with their construction contract. Within each major phase, all activities, tasks, or Definable Features of Work (DFOW) shall be identified that will require ___________.
CorrectIncorrect -
Question 3 of 9
3. Question
Contractor Quality Control and USACE Quality Assurance personnel. as part of their QC and QA responsibilities, shall document ___________.
CorrectIncorrect -
Question 4 of 9
4. Question
The project SSHO, at a minimum, must _________.
CorrectIncorrect -
Question 5 of 9
5. Question
Before beginning each work activity, the workers performing that work activity shall prepare an initial AHA. A ____________ is assigned to each step, to the risk that remains after controls have been applied (residual risk).
CorrectIncorrect -
Question 6 of 9
6. Question
A mishap is:
CorrectIncorrect -
Question 7 of 9
7. Question
The Contractor or USACE Project shall erect and maintain a Safety and Occupational Health bulletin board in a commonly accessed area in clear view of on-site workers. Among other items, the bulletin board shall contain:
CorrectIncorrect -
Question 8 of 9
8. Question
Frequent inspections/audits by a Competent Person of the work sites, material, and equipment, will be done to ensure compliance with the contract APP and the EM 385-1-1. These inspections/audits will be documented to include (select all that apply):
CorrectIncorrect -
Question 9 of 9
9. Question
All submitted and approved Activity Hazard Analysis will be continuously reviewed and modified as necessary to address ______________.
Select all that apply.
CorrectIncorrect